Three weeks have passed and things are finally starting to happen here. The first UPS-system is soon to be fully installed in the eye theater which is very pleasing to observe. The UPS in the eye theater is the smallest of the three systems which will be installed in this project. Few companies in Tanzania have good references in installations similar to our request, hence seeing the contracted company performing above expectation is relieving.
The eye theater has the following critical loads (rated) connected to the UPS:
- Lighting tubes 288 W
- Energy server bulbes 54 W
- Microscope machine 40 W
- Operation lights 300 W
- Anesthesia machine 280 W
- Total load: 962 W
Installed equipments:
- 1x Opti SP2400 24VDC Hybrid Inverter
- 2x Dayliff 195W 24VDC Solar module
- 2x Champion NP200-12 L sealed battery 200Ah, 12VDC
- 1x Steca PRS 20A charge controller
The system is also installed with a switch which makes it possible to have all loads bypassing the inverter. We figured it is best to have the system installed that way in case the inverter breaks. Better to be safe than sorry!
Eye theater
Three sockets are feed by the UPS and one socket is for air condition
Eye theater seen from patient entrance side
Solar panels connected to the Eye theater
Hope you enjoyed reading!
- Martin